|
In order to provide a competent
safe working environment and to comply with government and local
authorities Vivid Scaffolding set the following standards:
Labour Compliance
-
All scaffolding is
carried out by a competent work force who hold an appropriate
and valid CISRS and CSCS card relevant to the work activities
to be undertaken, and that such cards are produced as part of
the on-site induction process and are available for inspection
on request;;
-
All employees, including
delivery operatives, HIAB operators, etc, hold the relevant
skill card, e.g. CPCS and CSCS and , if appropriate, current
PTS or PASMA certificates;
-
Those involved in
the erection of recognised ‘system scaffolds’ are competent
and have appropriate training given by the manufacturer or a
recognised training body for that system, where available;
-
All employees receive
instruction in the requirements of the Work at Height Regulations;
-
Up to date skills
record will be made available, on request, including the training
records of any individual employee working the contract;
-
Once the labour resource,
including number of operatives, required skills, etc, for a
project have been agreed, the labour resource will be maintained
on the project for the duration of the programmed works;
-
The ‘erection crew’
(i.e. the gang of scaffolders involved in the erection, dismantle
or significant alteration of a scaffold) has the correct proportion
of qualified labour and, as a minimum, at least one qualified
scaffolder in every gang and where required by the nature of
the scaffold an advanced scaffolder; and,
-
A charge hand, who
must be a qualified scaffolder, is appointed for each erection
crew.
Management Compliance
-
All scaffolding works
are planned, managed and supervised at all times, to ensure
compliance with any main contractor and legislative requirements;
- Only nominated employees Vivid Scaffolding
and the Main Contractor provide and receive work instructions
and hand over certification. (Note: Under no circumstances is
a verbal hand over instruction acceptable.);
-
A risk assessment
and a method statement specific to the project prior to commencement
of on site work will be provided. The Risk Assessment and
Method Statement are to include a rescue and recovery plan..
Copies of the risk assessment and method statement will be
provided to the Main Contractor for review and comment, whenever
possible at least four weeks prior to the start of work on
site. A separate method statement should be generated for
dismantling, including exclusion zones provided around
the area. (Note: Under no circumstances is the ‘bombing’ of
any scaffold materials permitted on any sites.);
-
A site file to include
as a minimum the risk assessments and method statements, ‘Scaffold
inspection records’, records of any tie tests, updated design
and drawings, the inspection records of any harnesses and other
fall arrest equipment, machine inspection reports, and a full
list of all employees working on site, including details of
their CISRS and CSCS card, as appropriate
Minimum Scaffold Standards
In General
-
Materials brought
to a Main Contractor site are in good order such that it supports
a professional appearance.
-
Scaffold materials
arriving on site are checked as to their suitability, fitness
for purpose and are free from patent defects, and that any defective
materials are removed from site.
-
Specifically all materials
are supplied to the following minimum requirements:
(i) Scaffold tubing:
All scaffold tubing must comply with EN39:2001 and be a Type
4 tube having a wall thickness of 4mm. Preferably, but not essential
all tube to be high yield 3.2mm to BSEN10210-1:1994 S355JOH.
Under no circumstances are tubes of differing wall thicknesses
be mixed.
(ii) Scaffold boards:
All scaffold boards must comply with BS2482 ‘visually graded’.
It is the intention that only boards that comply with BS2482
‘machine graded’ will be sourced.
(iii) Fittings:
All load bearing scaffold fittings are to be drop forged and
must comply with BS1139 and EN74. (Note: The use of ‘Oyster
putlog clips’ is banned in all circumstances.)
(iv) Sheeting:
All sheeting must be flame retardant and to be provided to conform
to BS7955:1999 and be certificated to LPS1215.
(v) Debris nettings:
All scaffold debris nettings must be fire retardant and comply
with LPS1215.
(vi) Loading bay areas:
All scaffold loading bay gates are to be of proprietary ‘swing
over type’ that prevent persons getting near the edge when in
the open position and prevents falls of materials in the closed
position. Loading bays will have clear signage that provides
the user with adequate information regarding the appropriate
Safe Working Load.
(vii) Ladder accesses:
Where ladder accesses are within the working lift, precautions
must be in place to prevent falls. These include the use of:
a staggered guardrail arrangement as detailed in SG25:06 [NASC];
a proprietary hatch; or
a safe closing guardrail coupler.
For external ladder access up to a maximum of two lifts, a self-closing
safety gate is appropriate. All scaffold ladders must be supplied
to EN131/BS2037 for steel ladders and BS1129 for timber pole
ladders. Preference is given to use of metal section ladders.
(viii) External staircase
and accesses:
Use of proprietary staircases is to be favoured over ad-hoc
‘tube & fitting’ solutions. Unless supported by a risk assessment
completed by Vivid Construction, all scaffolds over three lifts
will be provided with a staircase where practical. All erection
of external staircases must be undertaken by competent labour,
i.e. CISRS qualified. Only genuine original equipment manufacturer
materials are used with staircases.
Proprietary system scaffold stairways must conform to BS EN
12811/12810.
Note: Access to all Scaffolding must meet the requirements as
specified in the Work at Height Regulations 2005.
(ix) Aluminium towers:
Aluminium towers can only be provided by an approved supplier
and only erected by a person who is PASMA trained.
(x) Stillages:
All scaffold stillages are to be in good condition and fit for
purpose. Stillages must be lifted as part of the load, i.e.
double wrapped with the slings, and must not be treated as lifting
accessory. All other bundling of scaffolding components must
be lifted in the same manner, i.e. double wrapped with the slings.
(xi) Transport, movement and
storage of materials:
Scaffold materials is delivered in a secure condition to allow
safe transport to the place of work. Scaffold tubes and fittings
will not be accepted for lifting unless they are banded or secured
in a suitable stillage. Only trained and competent slingers
will be allowed to sling loads, which must be carried out by
using good slinging practices, such as double wrapping with
chains or slings. At all times, materials used at the workplace
during erection, must be stored safely, in particular whilst
working at height where there is a risk of materials being displaced
or falling.
When moving materials along accommodation roads being used by
vehicular traffic or pedestrians a banksman on foot will accompany
the transport vehicle at all times. The driver of the transport
vehicle will obey the signals of the banksman at all times,
notwithstanding the driver’s statutory obligations to comply
with the requirements of the Road Traffic Act
(xii) Scaffolding tools:
Pre-use visual inspection of scaffolding tools must be carried
out by the user prior to the commencement of any scaffolding
works. Where there is a potential risk of scaffolding tools
falling and it proves impractical to reduce this risk (for example
by exclusion or working out of hours) the use of tool lanyards
will be used on all loose tools.
(xiii) Scaffold ties:
All scaffold ties must be physically identified on all scaffolds.
Ties must be tested by a competent person with calibrated equipment
, i.e. 5% of total or 3, whichever is the greater. The proof
load applied will be a minimum of 1.5 times the required tensile
load. Records of scaffold tie tests will be produced and maintained.
Such records will be included, as a minimum, the make, size
and details of the ties and their positions clearly specified
on a drawing. The testing regime for scaffold ties will be clearly
specified. Test results will be included and be cross-referenced
to the location of the anchor. Ties will be clearly marked by
the use of a tag to prevent accidental removal. If there is
doubt about the suitability of the base material to which the
anchors are to be fixed, then 5 No. anchors will be preliminary
tested to a load twice the tensile load in accordance with NASC
TG4. These anchor points will not be used to support the scaffolding.
(xiv) Harnesses, lanyards
and fall arrest equipment:
These will have, as a minimum, a quarterly recorded examination
undertaken by a competent person and be inspected visually each
time before use. All harnesses must have a unique identification
number that must be clearly visible. All harnesses shall be
no older than 36 months.
|